All Subdivision lodgements must be made through the NSW Planning Portal.
Payment
Application fee and long service levy is to be paid by credit card or direct debit, please advise in writing and we’ll call to make payment over the phone.
Completion Report
Addressing compliance with all 'General' conditions and 'Prior to the Issue of Construction Certificate' conditions detailed in your Development Consent.
Estimated Cost of Civil Works
Engineering Drawings
One set to scale and suitably sized for legibility. All engineering drawings are provided in the one PDF document.
Other Documents
As outlined in your Development Consent conditions under “General” or “Prior to the Issue of a Construction Certificate”, separated and named accordingly. These may include but are not limited to:
- Landscape Plan - Detailed and clearly identifies any trees to be removed
- Traffic Management Plan
- Construction Management Plan - Including dust control measures, erosion sediment control, construction access and hours of work, complaints management.
- Demolition Management Plan
- Plans are to show works to be undertaken outside site and/or stage boundaries, or within council road or public reserve, or on environmental lands (works on E3 Land require submission of a Works Management Plan).
Approved Environmental Lands Work Permit - For works in Council owned land zoned E2.
Consent of Third Parties - As per conditions of consent (RFS, RMS, OEH or Third Party Property Owners if works affect neighbouring property, etc.).
Please note that we’re unable to lodge your application without all documentation as listed above. It’s important to understand that all required information must be provided so that we’re able to undertake assessment. You’ll be advised if your application is incomplete through the Planning Portal.